TEL: (019467) 74716
Compensation Scheme Executive Secretariat, Sellafield Limited
Sellafield, Seascale, Cumbria CA20 1PG

NDA Sites

NDA Sites CSMB (Formally BNFL/UKAEA)                                                       

Progress report to the Compensation Scheme Council

The NDA Sites CSMB covers the following Sites / Employers

Site

Licensee

(Also scheme service provider if not Licensee where stated)

Dounreay

Dounreay Site Restoration Ltd (DSRL)

(Scheme service provided by UKAEA)

LLW Repository

LLW Repository Ltd

(Scheme service supplied by Sellafield Ltd)

Oldbury power station

Wylfa power station

Trawsfynydd power station

Chapelcross power

Hunterston A

Berkeley

Bradwell

Dungeness A

Hinkley Point A

Sizewell A

Harwell

Winfrith

Magnox Ltd.

(previously RSRL Ltd)

(previously RSRL Ltd)

(Scheme service provided via Sellafield Ltd, except for Harwell and Winfrith where the Scheme service is provided by UKAEA)

Sellafield and Calder works

Windscale.

Sellafield Ltd
Springfields.

Springfields Fuels Limited

(Scheme service provided via Sellafield Ltd)

Capenhurst

URENCO UK Ltd

Culham

(Scheme service provided by UKAEA)

With the exception of Culham and Capenhurst, these civil sites are owned by the Nuclear Decommissioning Authority (NDA) and are mostly focusing on decommissioning of nuclear power generation / reprocessing facilities, additionally Springfields site activities include fuel manufacture and the site is leased by NDA to Westinghouse Electrical Company LLC. Further information on the respective sites with links to Employer websites and further information can be can be found at:

www.gov.uk/government/organisations/nuclear-decommissioning-authority/about#ndas-estate

The Culham site is one of the world's leading fusion research laboratories and is owned and operated by the United Kingdom Atomic Energy Authority (UKAEA) which is also responsible for the management of historic liabilities relating to past UKAEA operations. Further information on UKAEA’s mission and the Culham site can be found at: https://www.gov.uk/government/organisations/uk-atomic-energy-authority

 

The board has its origins in 1982 upon the creation of the Scheme by BNFL, with other Employers joining over time such as the then UKAEA in 1987. Following industry changes in 2010 the Board was renamed to reflect the scope covered by the Board of primarily NDA Sites.

Annual summary of progress (April 2018 – March 2019)

The NDA Sites CSMB has continued the successful operation of the Scheme and this report notes the key issues since last year’s report to Council. It has met twice during the year:

  • 17 claims have been submitted this financial year compared to 25 reported in the last progress report. The majority (13 of 17) new claims arising have been under the Morbidity Agreement.

  • @ 1st May, 16 claims were ongoing through screening, of which 14 have been submitted within the financial year period. 3 claims are with Union representatives, awaiting closure/pursual

  • There are currently 6 successful cases progressing towards settlement/completion; 3 identified via the retrospection review (2 BNFL/Sellafield Ltd and 1 BNFL/UKAEA joint cases) plus 3 more recent claims (1 of which was identified during this financial year).
  •  4 cases arising from the cataract retrospection (4 BNFL/SL) are to progressed towards negotiation, whilst a further 2 cases (1 BNFL/SL and 1 UKAEA) still require medical diagnosis confirmation
  • 5 cases have been settled (all costs finalised and closed), 4 of which arose from the main retrospection exercise

The CSMB continues to monitor the achievement of target timescales focusing primarily on three key performance indicators:

KPI Target timescale % achieved

Time from receipt of claim to issue of screening data (Case Assessment Report)

6 months

70.6%

Time from receipt to closure for unsuccessful cases

 9 months

 78.6%

Time from receipt to determination for successful cases.

12 months

0%

Key causes of delays:

  • CoD provision (a recurring theme throughout the Scheme)
  • delays in the release of medical records from the NHS
  • delays in provision of data from employers (UKAEA & Springfields)

Progress on retrospection cases

2009 technical basis retrospection:

  • Out of the 19 cases where a claim was received 3 are still ongoing progression to settlement.

Cataract retrospection:

  • 10 identified potential cases
    • 4 are still awaiting response from a claimant.
    • 2 awaiting check of medical records for eligibility
    • 4 identify as successful and progressing to settlement.

Key points for information;

On 11th February 2019 ONR granted a nuclear site licence to Inutec Ltd (part of Tradebe) who occupy part of the Magnox Ltd Winfrith nuclear site and have been a specified company under the Scheme since it was divested from AEA Technology in 2006 (at the time the Organisiation was known as Waste Management Technology Ltd).  UKAEA are in discussion with Inutec Ltd to determine whether the Organisation should become a Scheme Employer in it's own right.

  

NDA Sites CSMB

7th June 2019